REPAIRING WORKS AND HANDING OVER OF THE REPAIRED HOUSES AT BOWBAZAR STARTED

AMAR KOLKATA METRO

KOLKATA

 

PRESS RELEASE

 

REPAIRING WORKS AND HANDING OVER OF THE REPAIRED HOUSES AT BOWBAZAR STARTED

 

Kolkata,11th February, 2024:

 

Metro Railway Authorities have started to repair the damaged houses and hand over the repaired houses at Bowbazar area. These houses, mostly poorly maintained and very old, were damaged during the underground tunneling work of East-West Metro in between Esplanade and Sealdah. After the disasters, Kolkata Metro Rail Corporation Ltd (KMRCL), the implementing agency, had promised to repair all the damaged houses and rebuild the totally damaged houses in this area after the completion of the construction work of this Corridor. 

 

In order to keep that promise, the damaged house of 6B Durga Pithuri Lane has already been repaired and handed over to the owners in habitable condition. The family of four members has expressed their satisfaction after getting back their house. At present, repairing works of two houses at 19/1A Durga Pithuri Lane and 12 Madan Dutta Lane are in advanced stage. Almost 70% of the repairing works of these two houses have been completed. It is also expected that these two houses will soon be handed over to their owners. Repairing work of another house, 1/4, Durga Pithuri Lane has just started. Repairing work of the damaged house at 19, Durga Pithuri Lane will start soon.

 

The engineers, while repairing these damaged houses, are grouting the foundations as well as for damaged walls they are doing High Tensile Steel (HTS) stitching and Apoxy grouting along with re-flooring where required. Due to this repairing work the longevity of these houses is going to increase.

 

 

Kausik Mitra

Chief Public Relations Officer





 








  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.