CASTING OF 2ND CONCOURSE SLAB COMPLETED AT BIMANBANDAR STATION on 24.03.2021
The construction work of Noapara-Barasat via Bimanbandar Metro project has been going on in full swing. In recent times, a significant progress of this project has been achieved. The Top slab casting of the proposed Bimanbandar Metro station was completed on 19.01.2021 earlier.
Casting work of the 2nd concourse slab of Bimanbandar station has been completed on 24.03.2021. This work started at 14:30 hrs on 23.03.2021 and after 17 hrs of concreting completed at 07.30 hrs on 24.03.2021. In this casting work, 3 concrete pumps along with 20 transit mixers were used. 45 labourers and 14 engineers were actively engaged towards completion of this work. 875 cubic meter concrete were consumed in this casting work.