LAST LEG OF TOP SLAB CASTING OF BIMANBANDAR STATION NEARING COMPLETION

LAST LEG OF TOP SLAB CASTING OF BIMANBANDAR STATION NEARING COMPLETION

The construction work of Noapara-Barasat via Bimanbandar Metro project has been going o­n in full swing. During Covid times and also in the new normal situation, a significant progress of this project has been achieved. 

Casting of the top slab of Bimanbandar station started o­n 26th June, 2020 during the lockdown period.  o­n 23rd January, 2021, top slab casting of Bimanbandar station has been completed. For completion of this work, 4590 MT steel has been utilized.   

The entire top slap casting work of this station is now nearing completion.











  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.