LAST LEG OF TOP SLAB CASTING OF BIMANBANDAR STATION NEARING COMPLETION
The construction work of Noapara-Barasat via Bimanbandar Metro project has been going on in full swing. During Covid times and also in the new normal situation, a significant progress of this project has been achieved.
Casting of the top slab of Bimanbandar station started on 26th June, 2020 during the lockdown period. on 23rd January, 2021, top slab casting of Bimanbandar station has been completed. For completion of this work, 4590 MT steel has been utilized.
The entire top slap casting work of this station is now nearing completion.