TOP SLAB CASTING OF BIMANBANDAR STATION COMPLETED on 19.01.2021
The construction work of Noapara-Barasat via Bimanbandar Metro project has been going on in full swing. During Covid times and also in the new normal situation, a significant progress of this project has been achieved.
Top slab casting of the proposed Bimanbandar Metro station has been completed on 19.01.2021. This work started at 10:30 hrs on 18.01.2021 and after 23 hrs of concreting completed at 09:30 hrs on 19.01.2021. In this casting work 1400 cubic metres of concrete were used with the help of 20 transit mixers and 3 pumps. 8 Quality Control Engineers and Supervisors along with 46 labourers worked tirelessly to accomplish this job.