FIRST TRIAL RUN CONDUCTED on NOAPARA-DAKSHINESWAR EXTENSION SMOOTHLY
The first trial run on Noapara- Dakshineswar extension stretch of North-South Metro has been conducted smoothly on 23.12.2020. This trial run started from Noapara at 10.30 a.m. Shri Manoj Joshi, General Manager, Metro Railway was present during this trial run. He inspected the entire stretch from Noapara to Dakshineswar via Baranagar from the Driving Motorman’s cab both in UP and DN direction.
After reaching Dakshineswar, Shri Joshi inspected the platforms, concourse, entry and exit gates, circulating area, lifts, escalators and other passenger amenities which will be provided at this station. Senior Officers of Metro Railway and RVNL were present in this trial run.