CASTING OF TOP SLAB OF BIMANBANDAR STATION COMPLETED
In the new normal situation, construction works of all the on-going Metro projects have been going on smoothly. Metro Railway has recently achieved a milestone by completing an uninterrupted 1500 cubic metre concreting work of top slab of Bimanbandar Metro station of Noapara-Barasat via Bimanbandar Extension Project.
This non-stop concreting work continued for 25 hours and the top slab with the dimensions of 36.3 metre X 40 metre X 1 metre (length X breadth X depth) was completed successfully. Three concrete pumps and twenty transit mixtures were used for completing this work. Forty eight labourers worked tirelessly maintaining all COVID-19 protocols to accomplish this job.