ROOF SLAB CASTING OF BIMAN BANDAR METRO STATION COMPLETED DURING LOCKDOWN
In spite of the nationwide lockdown, construction works of all the on-going Metro projects in the city have been going on smoothly. Metro Railway has recently achieved a milestone by completing uninterrupted 1481.5 cubic metre concreting work for Roof Slab of Bimanbandar Metro station of Noapara-Barasat via Bimanbandar Extension Project.
48 engineers, operators and workers worked in tandem and completed this job in two shifts in spite of COVID-19 lockdown. While executing this work they all maintained social distancing and other covid-19 protocols.
The concreting work started on 10.08.2020 and completed on 11.08.2020.