162913-11-2023
KOLKATA
SERVICES LIKELY TO START ON THE ENTIRE EAST-WEST METRO ROUTE IN JUNE, 2024

METRO RAILWAY

KOLKATA

PRESS RELEASE

SERVICES LIKELY TO START o­n THE ENTIRE EAST-WEST METRO ROUTE IN JUNE, 2024

Kolkata, 13.11.2023:-

East-West Metro or Green Line of Amar Kolkata Metro is going to change the transport scenario of Kolkata and its twin city Howrah. Already services are running o­n Salt Lake Sector V to Sealdah stretch of this Corridor successfully. Passengers coming from suburbs are availing comfortable Metro services from Sealdah station now. Very soon passengers of suburban areas will be able to enjoy Amar Kolkata Metro services from another iconic station of Indian Railways i.e. Howrah. In order to make the dream of a comfortable and fast Metro services under the river Hooghly a reality, every possible steps are being taken. At present the section from Howrah Maidan to Esplanade is almost ready for the commercial service and trial runs o­n this stretch are being conducted regularly. Shri P Uday Kumar Reddy, General Manager, Metro Railway has also been monitoring the progress of the work o­n regular basis.

Due to some unfortunate occurrences during the construction of underground cross passages at Bowbazar, o­n the 2.5-km long stretch in between Sealdah and Esplanade stations disasters have struck. As a result, the progress of this project has been affected. But now the problem has been resolved without compromising passengers’ safety and the trial run in between Esplanade and Sealdah is likely to start in the beginning of the next year. If everything goes according to the plan then passenger services o­n the entire stretch of East-West Metro from Howrah Maidan to Salt Lake Sector V may start in June 2024.

In order to mitigate the problem at Bowbazar, necessary steps are being taken without compromising with the passengers’ safety. Kolkata Metro Railway Corporations Ltd. (KMRCL) had submitted an alternative plan which has been approved by the Fire Department of West Bengal.

Shri Kausik Mitra, Chief Public Relations Officer, Metro Railway has informed, “The remaining work at Bowbazar will be completed at the earliest. In the beginning of the next year the trial run in between Sealdah and Esplanade may likely to start. It is expected that commercial services from Salt Lake Sector V to Howrah Maidan will start in June, 2024.”

Kausik Mitra

Chief Public Relations Officer





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.