CONSTRUCTION WORK OF NABADIGANTA METRO STATION TO START FROM 31.07.2023 (MONDAY)

METRO RAILWAY

KOLKATA

PRESS RELEASE

CONSTRUCTION WORK OF NABADIGANTA METRO STATION TO START FROM 31.07.2023 (MONDAY)

Kolkata, Date: 29.07.2023

Good News for Metro commuters and all the Kolkata Metro lovers!!

After the all important traffic diversion (Stage – I) at Nabadiganta crossing granted by Bidhannagar Traffic Police Department, Rail Vikas Nigam Ltd (RVNL) is gearing up to start the construction work of proposed Nabadiganta Metro station (popularly known as Technopolis) of New Garia- Airport via Rajarhat Metro Corridor from 31.07.2023 (Monday). For this, necessary plants, machineries and manpower are being arranged and mobilised. It will be a big boost for this project after overcoming seemingly unassailable hurdles. Due to some land related issues, 2791 sq. meter of fresh land were acquired from Kolkata Metropolitan Development Authority (KMDA) and the earlier proposed location of this station has been shifted to its present location. Another 536 sq. meter of land will be acquired from Airports Authority of India (AAI) very soon for construction of this station. RVNL has already made necessary payment of the lease money for that piece of land to AAI.

As the work is going to start from the last day of this month, executing agency RVNL has been aiming to complete the construction work by December, 2024. This upcoming Nabadiganta Metro station will be 180-meter long and 35-meter wide. For this, 294 piles, 36 pile caps and 46 columns are required to be constructed. Utilising this traffic diversion which has been granted for nine months, RVNL will also construct 10 piers at this location for the project. o­ne concourse level, o­ne platform level and 4 entry structures will be constructed for this station.Once commissioned Nabadiganta Metro station will be the Gateway to New Town.

Kausik Mitra, Chief Public Relations Officer, Metro Railway has thanked the local authorities for granting the all necessary traffic diversion at Technopolis to enable RVNL to start the station construction work. He has also appealed to all the stakeholders to co-operate for smooth execution of this project and ensuring a better tomorrow.

Kausik Mitra

Chief Public Relations Officer





 





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.