CONSTRUCTION WORK OF PHASE-II OF NOAPARA-BARASAT VIA BIMANBANDAR METRO PROJECT GOING ON

METRO RAILWAY

KOLKATA

PRESS RELEASE

CONSTRUCTION WORK OF PHASE-II OF NOAPARA-BARASAT VIA BIMANBANDAR METRO PROJECT GOING o­n

Kolkata, Date: 23.07.2023

Construction works of different Metro Projects in the city have been going o­n in full swing. Shri P Uday Kumar Reddy, General Manager, Metro Railway has been constantly monitoring the progress of works of different Metro projects and personally visiting the project sites for their speedy completion.

Noapara-Barasat via Bimanbandar Project, Phase-II work has been going o­n round the clock. Though there are some issues such as delay in handover of Airports Authority of India land inside the operational area, height restrictions in the Air Funnel Zone, shifting of West Bengal State Electricity Distribution Corporation Limited’s 33 KVA cables and diversion of traffic o­n National Highway-12 at multiple stretches etc. which have been hampering the progress of this Project, still Phase-II work of this Project beyond Bimanbandar station yard upto New Barrackpore is going o­n. o­n 19.07.2023 a challenging work of pile casting at the congested Bankra More near NH-12 has been done successfully. For casting this pile, 55-meter deep boring was done first with the help of 35-meter high Hydraulic Rig. After that 2.21 MT reinforcement cage was lowered and 44 cubic meter concrete were cast to construct this 1.2-meter diameter and 55-meter deep pile with the help of 35-meter high crane. This work started at 10:00 am o­n 18.07.2023 and completed at 10:00 am o­n 19.07.2023.

The construction of this pile was very challenging at the very busy Bankra More. With meticulous planning and deploying required plants and machineries it has been done smoothly.  During the entire construction work Traffic Marshals were deployed to ensure smooth traffic flow o­n busy National Highway 12.

Shri Kausik Mitra, CPRO, Metro Railway has thanked all stakeholders for their support in executing this dream Metro Project which will touch the city airport.

 





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.