COMPLETION OF BOTTOM SLAB CASTING AT
BIMANBANDAR METRO STATION
Kolkata, Dated 30.08.2021 :
Works of the all Metro projects in the city have been going on smoothly even during the present restriction imposed due to COVID pandemic. A major progress of Noapara to Barasat via Bimanbandar Metro project has been achieved on 29.08.2021 as the casting work of the bottom slab of 64 meter long RCC Box tunnel has been completed. For this work, 632 cubic meter concrete have been casted below the very busy VIP Road and Airport Entry Road.
It was a very challenging work as traffic movements on these two very busy roads were not disturbed during this work, except a few diversions. This casting work was started at 16.50 hrs. on 27.08.2021 and it was completed on 29.08.2021 at 00.53 hrs.