218313-02-2025
KOLKATA
COMPLETE BLOCK ON GREEN LINE STARTING FROM 13.02.2025 TO 16.02.2025 AND 20.02.2025 TO 23.02.2025

AMAR METRO

KOLKATA

PRESS RELEASE

COMPLETE BLOCK o­n GREEN LINE STARTING FROM 13.02.2025 TO 16.02.2025 AND 20.02.2025 TO 23.02.2025

Kolkata, Date:-12.02.2025

On successful completion of tunneling work between Esplanade and Sealdah stations, Metro Railway, Kolkata is going to grant complete Traffic Block in two spells starting from tomorrow i.e. from 13.02.2025 to 16.02.2025 and again from 20.02.2025 to 23.02.2025 (four days each including Saturdays and Sundays) for testing of Communication Based Train Control (CBTC) System o­n the entire Green Line Metro Corridor from Howrah Maidan to Salt Lake Sector V. 





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.